What is the expected output of a team of four people working with AM 800 and AM 810 finish coats?
A team is supposed to deliver around 100 m2 of finished coat per day, in case of manual application. A team working with a hydrodynamic unit is supposed to deliver around 300 – 500 m2 of finished coat per day depending on people’s skills and the way the substrate is prepared.